One issue was resolved on every working day out of 382 projects reviewed by PM

The Pro-Active Governance and Timely Implementation (PRAGATI) platform has reviewed the implementation of 382 projects, with 3187 issues raised and 2958 of them being resolved. In other words, one issue was resolved every working day.

Listen to this article
The PRAGATI initiative was launched in 2015 by Prime Minister Narendra Modi to address the chronic problem of large time and cost overruns in India’s public projects and welfare schemes. The PRAGATI mechanism deploys a technology-based platform for Project Monitoring, Citizens’ Grievance Redressal and Reviewing Scheme implementation through active collaboration of Central Ministries and State Governments.
The initiative aimed at improving Centre-Centre and Centre-State coordination in order to fast-track critical infrastructure projects facing Issues and Bottlenecks. It also focused on improving outcomes in flagship schemes showing sub-optimal performance or requiring structural reforms and assessing and resolving citizen grievances across sectors.
Prime Minister chairs PRAGATI review meetings directly with Chief Secretaries of States & Secretaries of Central Ministries/Departments to address issues in specific Projects & Schemes.
50 such review meetings have been held so far, as per a presentation made by the Cabinet Secretary and the other Departmental Secretaries in a media briefing on Friday. The outlays in capital expenditure have increased 3.6 times to Rs 15.53 lakh crore as per budget estimates for 2025-2026 from Rs 4.26 lakh crore in 2014-2015. Issues relating to land acquisition and law and order, among others, were resolved.
Out of the 382 projects reviewed by the Prime Minister, 114 were from the roads and transportation sector, while 109 were railway projects; other projects pertained to power, petroleum, and other areas.
The PRAGATI platform has accelerated the implementation of over 3300 projects worth over Rs 85 lakh crore and  61 Government schemes, including One Nation-One Ration Card and the Swachh Bharat Mission, among others. Overall, the system received 7735 issues, and 7156 of them were resolved.
Overall, 427 Railway Projects faced 1568 Issues, out of which1437 issues have been resolved via PRAGATI-led Ecosystem. 1463 road and highway Projects faced 2095 Issues, out of which 1968 issues have been resolved via the PRAGATI-led ecosystem. 416 Power Projects faced 885 Issues, out of which 803 issues have been resolved via PRAGATI-led Ecosystem.

Latest

A biography on SNN Sankaralinga Iyer

The biography was authored by veteran journalist K Balakumar....

Activity Galore

Godrej Properties bought 47 acres off OMR for a...

When Numbers Tell A Tale…

 Ask the mandarins at TAFE (Trac­tors and Farm Equipment...

Managing Power

With mercury rising, Tamil Nadu’s power demand is hitting...

Newsletter

Don't miss

A biography on SNN Sankaralinga Iyer

The biography was authored by veteran journalist K Balakumar....

Activity Galore

Godrej Properties bought 47 acres off OMR for a...

When Numbers Tell A Tale…

 Ask the mandarins at TAFE (Trac­tors and Farm Equipment...

Managing Power

With mercury rising, Tamil Nadu’s power demand is hitting...

Minister Keerthana Chairs Budget Consultation Meeting

Detailed discussions were held on the Department's ongoing development...

A biography on SNN Sankaralinga Iyer

The biography was authored by veteran journalist K Balakumar. The Tamil translation of the book was also released simultaneously. The Tamil translation was done...

Activity Galore

Godrej Properties bought 47 acres off OMR for a plotted residential project, while Arihant Foundation and Housing acquired a prime Anna Salai site, adjacent...

When Numbers Tell A Tale…

 Ask the mandarins at TAFE (Trac­tors and Farm Equipment Ltd.). They will unhesitatingly vouch for it. Indeed, the flagship company of the Chennai-based Amalgama­tion...